S. No | Topics |
1. | (a):Introduction to Health and Safety measures. in Engineering Surveying Lab. (b):Introduction to various Surveying instruments. (c):Various methods and equipmentused for measuring distance. |
2. | To range out a survey line when the two ends of a line are inter-visible from each end, and when two end points are not inter-visible from each end (Direct and Indirect Ranging). |
3. | To measure the horizontal distance between two terminal stations by different methods when the ground is flatand to determine the horizontal distance between the two terminal stations on a sloping ground by (I) Stepping Method (II) Using Abney Level. |
4. | To set out the base line and Perpendicular line / Offsets in the field. |
5. | Introduction to Automatic level and temporary adjustment of Automatic level. |
6. | To collect data for Profile Levelling and cross sectional leveling of a proposed road using Auto Level. |
7. | To draw profile of a road (L-Section) and Cross-sections of a proposed road from obtained level data. |
8. | Introduction to theodolite and its temporary adjustment and to determine the Horizontal angles, vertical angles and bearing of lines. |
9. | To determine the independent coordinates of an existing building by theodolite traversing. |
10. | To determine horizontal distances by tacheometric Surveying when the line of sight is horizontal. |
11. | To set out the Simple Circular Curve by deflection Angle method. |
12. | To determine R.L at top of elevated object by Trigonometric Leveling. |
13. | Orientation of Total Station and its Adjustment. |
14. | To collect data for contour map of a given area of land by using total station. |
15. | To set out layout of a building by using coordinate method with the help of total station. |
16. | To perform an open-ended lab. |